Earls Court to West Kensington - District Line
Client: BSR metro
Finished: In progress at time of photograph
Duration: 12 weeks
Site access was a problem at West Kensington, and with
approximately 100 m3 to remove from the cutting during reprofiling,
the best solution was to use conveyors to move the
excess material to awaiting skips.
When re-profiling of the embankment is complete, BSR metro
are to undertake soil-nailing as a stabilisation measure.
 |
The vegetation clearance
team makes progress along the cutting removing surface vegetation. |
|
 |
Conveyors move the excess
material to awaiting skips. |
|
 |
The final embankment profile
can be seen as the conveyors are removed before soil nailing. |