Contracts
Chigwell to Grange Hill - Central
Line
Client: BSR metro
Finished: In progress at time of photograph
Duration: 24 weeks
 |
Site access provisions: a temporary bridge (provided by BSR
metro) over Chigwell Brook and haul road to embankment |
|
 |
Enabling works
at Chigwell |
|
 |
The access ramp
and piling platform is constructed from granular fill. The
embankment is supported using scaffold poles and plywood |
|
 |
The access platform is constructed
along the pile-line. It is removed following piling to allow
final embankment regrading and topsoil placement. |