Contracts
Highgate to East Finchley - Northern
Line
Client: Cementation Foundations Skanska (CFS)
Finished: May 2004
Duration: 14 weeks
This contract involved the stabilisation of the A1 embankment to
prevent it from subsiding
into Highgate Station car park.
 |
View towards A1
from Highgate Station Car Park |
|
 |
Access to pile
locations is enabled |
|
 |
Following piling by CFS, a capping beam is
placed over the piles |
|
 |
This is filled
with reinforcing steel and concrete |
|
 |
The access ramps
are then removed |
|
 |
The slope is re-profiled
using compacted granular fill material before topsoil is
added and re-planting of vegetationcan take place. |
|
 |
Final view looking
toward the A1 from Highgate Station |